US Data Center Financing & Community Risk Model

Project Finance Underwriting Stress Test Workbench
Regional Presets:
Base Assumptions
Project Name
Total Capex ($M) $850M
Facility Capacity (MW) 120 MW
Debt-to-Equity (LTC %) 65.0%
Debt Interest Rate (%) 6.80%
PPA Rate ($/MWh) $62/MWh
Community & Grid Stress Factors
Zoning & Approval Delay (Months) 9 mos
Grid Interconnect Queue Delay 12 mos
Noise/Water Mitigation Capex ($M) $25M
Stressed DSCR
1.11x
Base Case: 1.42x
Covenant Warning
IDC Expansion
+$34.68M
Added Interest During Construction
High Interest Drag
Stressed Equity IRR
10.4%
Base Case: 14.8%
Target Compression
Lender Risk Rating
Moderate-High Risk
Delay & Covenant Breach Risk
Underwriting Watch
Capex & IDC Waterfall ($M) Base vs Opposition Stressed
Debt Service Coverage Ratio (DSCR) Timeline 1.20x Min Covenant Threshold
DSCR Sensitivity Matrix: Interconnect Delay vs Zoning Delay Highlighted Operating Point
Underwriting Analysis Output Proof: Lender Risk Rating: Moderate-High Risk (Delay & Covenant Breach Risk)
DSCR Delta: -0.31x