Data Centre Pipeline Deflator

Speculative Interconnection Queues vs Power Grid Delivery Reality

Stage-Gate Parameters N. Virginia (PJM)
14.5 GW
42%
3.5 yrs
68 / 100
82 / 100
25%
Capacity Attrition Waterfall (GW) Real vs Announced
Announced PR 14.50 GW
Phantom Bookings -6.09 GW
Grid Bottleneck -2.18 GW
Deliverable Reality 4.82 GW
Political Rhetoric vs Tax Concession Settlement Matrix
Public Grandstanding Moratorium Threat: High (68 / 100)
Tax Concession De-escalation Power: -32.8 pts
Behind-the-Meter Power Neutralization: -17.5 pts
Effective Political Friction Retention: 34.2% (De-escalated)
The Economist Core Finding: Over 40% of Northern Virginia data centre queue entries represent the same developer filing redundant requests across 3+ substations. Once municipal tax windfalls ($120M+/yr) are factored in, local political resistance retreats, leaving deliverable energization at ~4.82 GW by median year 2029.