1-GW Campus Power & Thermal Topology Map
Select any electrical tier below to inspect supplier shares, lead-times, and alternative vendor hubs.
Step-Up Transformers & Substation Switchgear
Hardware Bill-of-Materials & Bottleneck Audit Table
Calibrated against global hyperscaler procurement logs and power delivery timelines.
| Hierarchy Stage | Component Tier | China Supply % | Current Baseline Lead Time | Geopolitical Extension | CapEx Weight | At-Risk CapEx ($M) | Delayed MW | Domestic Alternatives |
|---|
Saved campus component exposure arithmetic
Read the explanation
Saved campus capital eight point five billion times transformer weight twenty-two percent allocates one point eight seven billion dollars to that tier. Bars compare whole campus and allocation at fifty pixels per billion dollars. Supplier shares and costs are saved assumptions rather than current verified procurement. Allocated one point eight seven billion multiplied by saved China supply share point seven one gives one point three two seven seven billion. Bars compare tier capital and computed exposure at three hundred pixels per billion dollars. This is modeled accounting exposure, not a measured disruption probability or guaranteed loss. Saved one gigawatt converted to one thousand megawatts times tier delayed factor point four two times share point seven one gives two hundred ninety-eight point two, rounded to two hundred ninety-eight. Bars compare campus capacity and unrounded delayed estimate at point five pixels per megawatt. Complete native full bill-of-materials JSON/reset and footer placement preserved; causal supply risk unproved.