Review Status
Compliant Timeline
Meets 30-day statutory threshold
Notice Deadline
2026-10-02
30 calendar days before work starts
Required Notice Period
Federal civil court rule standard
Compliance Score
Proposed Physical Modification
Configure scope, categorization, and execution schedule
Statutory Timeline & Milestone Track
30-day statutory standstill window mapping
Notice Dossier Submission
2026-09-20Submission of architectural plans, engineering elevations, and landmark impact assessment to federal docket.
Statutory Notice Deadline (§ Judge Injunction) Mandatory
2026-10-02Latest legally allowable date to publish notice (strictly 30 days prior to physical disturbance).
Public Review & Historic Agency Comments
2026-10-02 to 2026-10-25Commission of Fine Arts (CFA) & National Capital Planning Commission (NCPC) advisory review period.
Earliest Authorized Construction Inception
2026-11-01Physical work may commence if no interlocutory injunction or stay is filed during notice window.
Federal Landmark Review Checklist
Toggle criteria to verify court mandate conformance
This planning tool directly operationalizes the recent federal court directive mandating the John F. Kennedy Center for the Performing Arts to issue formal 30-day notifications prior to executing major architectural changes. As the national cultural memorial to President Kennedy, the facility is subject to strict judicial and landmark preservation review to balance modernization with historical monument integrity.