Nevada Federal Basins:
Lat: 36.41° N, Lon: -114.94° W | Scale: 1:24,000
3. Interconnection & Feasibility
Live generation, capex & intertie
BLM Priority SEZ: Clean Permitting Zero tortoise buffer overlap. 100% inside BLM streamlined leasing corridor.
Gross Land Area
2,700 ac
6.0 ac / MWac
Annual Generation
1,120 GWh
Cap Factor: 28.4%
Intertie Distance
3.2 mi
$6.4M Gen-Tie Line
Estimated LCOE
$34.8 /MWh
Federal ITC (30%) inc.
Nevada Summer Solstice Generation (MW) 450 MW Peak
Ready. Adjust array footprint or drag site on the map.

Federal Energy Act of 2020 & BLM Siting

The Bureau of Land Management (BLM) Western Solar Plan designates Priority Solar Energy Zones (SEZs) across Nevada where programmatic environmental impact statements (PEIS) reduce National Environmental Policy Act (NEPA) review timelines from 4 years down to under 14 months.

Desert Tortoise (Gopherus agassizii) Mitigations

Projects encroaching upon federally listed Mojave desert tortoise critical corridors require compensatory mitigation land acquisitions at ratios up to 3:1, plus costly transmigration fencing and wildlife biologist oversight, adding between $18M–$45M to utility-scale development capex.

NV Energy Greenlink & CAISO Intertie

Nevada’s high solar insolation (DNI > 7.5 kWh/m²/day) makes it a critical exporter to CAISO (California) and the Desert Southwest. Interconnecting to 500kV lines like Greenlink West requires dedicated gen-tie lines costing ~$2.0M/mile plus substation bay expansions.

Enjoy this tool? Build your own with Super