Announced 2-Week Window Civil Logistics

Interior Secretary Doug Burgum announced on Thursday that site excavation will commence over the next two weeks. Civil engineering sequence required to safely execute a 250-foot monumental arch foundation:

  1. Phase 1: Mobilization & Geotechnical Borings (Days 1–5)
    Drill rigs execute 80-ft core borings across pier footprints to verify bedrock depth and water table pressure before heavy yellow iron mobilization.
  2. Phase 2: Clearing & Utility Interceptor Trenches (Days 6–10)
    Securing site perimeter, relocating sub-surface electrical/storm lines, and grading staging pads for dual 400-ton crawler cranes.
  3. Phase 3: Mass Earthwork & Shoring (Days 11–24)
    Excavating 28,650 cu yd across twin foundation pits. Requires ~160 tri-axle truck round-trips daily to dump haul sites without regional traffic gridlock.
  4. Phase 4: Mud Mat & Caisson/Mat Footings (Days 25–45)
    Pouring 4-inch unreinforced blinding mud mat, installing high-strength rebar cage grid, and continuous concrete mass pour.

Monumental Scale Benchmark

Monument Location Height (ft) Relative to 250'
Proposed Triumphal Arch Washington DC (Proposed) 250 ft 100.0% (Baseline)
Arc de Triomphe Paris, France 164 ft 65.6% (-86 ft)
Washington Monument Washington DC 555 ft 222.0% (+305 ft)
Gateway Arch St. Louis, MO 630 ft 252.0% (+380 ft)
Marble Arch London, UK 45 ft 18.0% (-205 ft)
*Paris Arc de Triomphe stood as the world's tallest triumphal arch from 1836 to 1982 until the Arch of Triumph in Pyongyang (197 ft). The proposed 250-foot arch would exceed both.