Max Annual Cadence
15 / yr
Limited by Pad 2 Turnaround
Pad Infrastructure Duty
98.6%
Active Pad Occupancy
Flight 14 (Ship 42) Window
Early Sept
Megabay 2 integration ready
Primary Limiter
Pad 2 Refurb
Deluge / OLM downtime
Multi-Pad & Stacking Timeline (180-Day Rolling Manifest)
Megabay 2 / Stacking
Pad 2 Operations
Pad 1 Operations
Deluge / OLM Refurb
Pipeline Bottleneck Analysis
Capacity: 100% Target Met
Single-Pad Operational Constraint: Pad 1 is currently in deep renovation returning in 2027. Pad 2 handles 100% of launch deluge recovery, cryo chilling, and flight ops, limiting max yearly cadence.
Vehicle Stacking (Megabay 2 / Gigabay)
16 days / stack (Healthy)
Pad Infrastructure Turnaround (OLM / Deluge)
24 days / cycle (Bottleneck)
Tank Farm Cryogenic Recharge
36 hours / cycle (Nominal)
Simulated Flight Manifest
Showing next 8 flights
| Flight | Vehicle | Pad | Target Day | Turnaround |
|---|