Flight 14 NET Window
Sept 4 - Sept 10
Ship 42 + Booster 16 in Megabay 2
Pad 2 Turnaround Cycle
24 Days
Rollout to Lift-off
2026 Single-Pad Cadence
13 Launches/yr
Bounded by Pad 2 recycle & cryo
2027+ Dual-Pad Capacity
28-32 Launches/yr
Pad 1 + Pad 2 synchronized ops
Starbase Pad Schedule & Flight 14 Milestones
Megabay 2 Prep
Pad 2 Cryo & Static Fire
Launch Window
Pad 1 Renovation
Primary Operational Bottleneck
With Pad 1 offline for major rebuild until 2027, total Starbase flight rate is bound by Pad 2 cryogenic tank farm subcooling throughput and water deluge refurbishment cycle (5-7 days between static test and orbital flight).
Target Manifest Schedule
| Flight | Ship / Booster | Pad | NET Target | Status |
|---|