Simulation Parameters
LIVE MODEL
Cadence Telemetry
TX-01
Flight 14 Launch Target
Sep 06, 2026
Early September Window
Turnaround Cycle
23 Days
Nominal Fast-Track
Active Pads
1 (Pad 2)
Pad 1 Offline
Annualized Cadence
15.8 / yr
Single-Pad Ceiling
Bottleneck Critical Path
Booster Proof & Static Fire
Consuming 34.8% of pad turnaround
Starbase Multi-Pad Operations Schedule (Gantt)
● Pad 2 (Active)
● Pad 1 (Renovation / 2027)
▲ Launch
Flight 14 Flight Readiness Staging Gates
Click milestone to toggle status
Projected Starship Launch Manifest
Flight 14 through Flight 19 Pacing
| Mission | Pad | Processing Start | Stack / WDR | Target Launch | Cadence Delta | Operational Phase |
|---|