Target Launch Date (Flight 14)
Sep 04, 2026
Active Launch Infrastructure
Pad 2 Active (Pad 1 Reno)
Projected Annual Cadence
15.2 flights/yr
Primary Bottleneck
Pad Turnaround
Starbase Launch & Turnaround Manifest (Gantt Projection)
Pad 2
Pad 1 (2027+)
Pad 1 Renovation
Operational Insight: Pad 2 turnaround is currently the critical path (24 days). Vehicle staging (Ship 42 / Megabay 2) completes in 10 days, remaining queued until pad clearance and cryogenic verification.
Flight Schedule Details
| Flight | Ship / Booster | Staging Bay | Pad Assignment | Cryo / Static Fire | Target Launch |
|---|