Operational Presets
Milestone Days Allocation
Pad Strategy
Vehicle processing: Ship 42 in Megabay 2. Pad 1 offline for 2027 deep refit. All immediate launch cadence is serialized through Pad 2.
Flight 14 Milestone Timeline & Critical Path
D3.js Dynamic Gantt
Starbase Pad 2 (Active)
ACTIVE LAUNCH PAD
Assigned to Flight 14. Supports Ship 42 / Booster stack, static fire runs, and tower catch arm integration.
| Phase | Vehicle | Allocated |
|---|---|---|
| Cryo Proof | Ship 42 | 3 Days |
| Static Fire | Ship 42 + Booster | 6 Days |
| Final Stacking | Flight 14 Stack | 2 Days |
Starbase Pad 1 (Renovation)
OFFLINE UNTIL 2027
Undergoing major structural overhaul and deluge upgrades for next-gen Starship vehicle cadence in 2027.
Cadence Impact: 100% of orbital test operations concentrated on single pad. Zero parallel pad static fires possible.