Day 3 Throughput
6.0 mbpd
50% Pipeline Target Achieved
Week 6 Throughput
12.0 mbpd
Full 100% Aramco Baseline Restored
Total Cumulative Deficit
218.4 M bbls
Cumulative crude supply offline
Market Recovery Status
On Track for 6-Week Full Recovery
Supply normalized in 42 days
Throughput Ramp & Supply Deficit Curve
Horizon: 42 Days (6 Weeks)
Initializing Canvas Telemetry...
Repair Phase Milestones
Phase 1: Immediate Triage
Incident Shock
Day 0: 2.4 mbpd throughput (80% cut)
Phase 2: Fast Pipeline Bypass
50% Pipeline Resumption
Day 3: 6.0 mbpd restored
Phase 3: Deep Facility Repairs
100% Full Capacity
Day 42: 12.0 mbpd restored